Client: NISOC
Type of project: PC
The subject is transferring multi way saline oil to Gachsaran 1 production unit, separating the present production equipment in production unit, designing, constructing, and installing degassing tank, constructing 16 and 6 inch pipelines for transferring oil and connate water respectively from Gachsaran 1 production unit, Gachsaran 2 desalting unit connate water respectively from Gachsaran 1 production unit, Gachsaran 2 desalting unit, constructing 8-inch pipelines of Northeast, Southwest, burners.
Connection of pipeline 4 inch, waste disposal to new pipeline, transmission of associated water, construction of pipeline 8 inch SW FLARE and minor changes related to connecting pipeline 8 inch NE FLARE.