Gathering and injection of associated gas of Cheshmekhosh

Gathering and injection of associated gas of Cheshmekhosh

Location: 70 Km West of Andimeshk

Brief description of project goals:

Perform basic of design review, detailed design, purchase and supply of goods and equipment required of the project, packing and transportation of the land and sea, disembarkation, customs and clearance, insurance, operations of construction and architectural and mechanical and installation, delivery and guaranty within period of warranty, observing all issues of salty, health, environmental in form of (EPC) for gathering and injection of associated gas of cheshmehkhosh.

Description of field:

The project uses of 2 gas wells for injection gas in the field of Cheshmehkhosh

Work explanation:

Designer gathering and upgrade pressure of associated gas of Cheshmehkhosh’s oil which is part of the overall plan development of Cheshmehkhosh, in the form of a separate project is defined includes the following parts:

Bank 1: design of gathering and promotion of pressure step by step of sweetening with oil of tiers A, B development production unit of Cheshmekhosh. Natural gas during 3 stages by 6(3+3) (screw) are collected and during 3 stages by 6(3+3) reciprocating is ready for transmission to the injection pipeline for using as injection gas to the fields of Cheshmekhosh. The initial pressure 0.14 barge and final pressure 340 barge and final amount is 8/55 MMSCFD.

Bank 2: design of gathering and promotion of pressure step by step of sour gas with oil of tier C production unit development of Cheshmehkhosh. Natural gas in the 3 stages by 6(3+3) screw are collected and during 3 stages by 4(2+2) reciprocating is ready for transmission to the short pipeline (for transmission to the factory NGL-3100 for treatment processor), the initial pressure 0.14 barge and final pressure is 3/81 barge and final amount is 231/44.

Home > OngoingProjects > Gathering and injection of associated gas of Cheshmekhosh
0 Comment

Write a Reply or Comment