CLIENT: National Iranian South Oil Company (NISOC)
TYPE OF PROJECT: Seismic
THE GEORAPHICAL LOCATION: 200 Km South of Ahvaz between 4province of Khuzestan, Kohgiloyeh and Boyrahmad, Bushehr, Fars
Brief description of project goals:
The aim of the project is 3D seismic survey of oil fields of Bibihakimeh, Seyahmakan, Kilver Karim and also providing related services with desert and rugged mountains so that the topography area was changing from flat area to mountainous, but 70% of area is mountainous (elevation changes from 10 to 1200m) and 3D seismic survey data is 2/024 square Km.
Work explanation:
The first step of the project was taken with networking operation area and in the next step LVL, UP HOLE and also was started operation mapping and during various issues group op operation mapping and drilling group has worked and data survey began officially and by the way, site equipment was done before the start of operations.